In this article, you will learn how to model the construction of a WTG. Please follow the below step by step guide. Prior to start your modelling you need...
The probability-weighted timelines are calculated from a set of individual timelines from each of the single simulation runs. The timeline for the single si...
The statistical summary displays the mean project duration, the standard deviation and the standard error; these values are in days. The "Mean proje...
Root cause (asset downtime) The root cause of downtime algorithm implemented in SHORESIM™ allows you to track the loss of time and the cause of wind farm a...
The weather downtime assessment chart shows the weather downtime per month measured in the simulation runs. NOTE: as seen in the example above, the Heavy L...
The transfer vessel utilisation shows the percentage of days the transfer vessel has been sailing per month. NOTE: as seen in the example above, the Serv...
The asset cycle graph shows the number of hours used on different installation steps of the cycle per asset type. The data is the sum of all durations per s...
The vessel cycle graph shows the number of hours used on different installation steps of the cycle per vessel. The data is the sum of all durations per step...
In this article, you will learn how to add, edit or replace a port and/or offshore base. When setting up a case, it is important to have a port or offshore...
This article will teach you all about the last step in setting up your case: Strategy. In the Strategy Menu, you can fill in high-level information for th...