This article will guide you on how to add an Anchor handling vessel (AHV) to your Construction case. Adding an AHV Editing an AHV Adding an AHV 1. Op...
This article will guide you on how to add and edit a component transfer vessel to your CONSTRUCTION case. Adding a Component transfer vessel Editing a C...
In order to set up the towing vessels' processes, you will have to edit the towing vessel (tug) by clicking on it, and then going to the Processes tab. ...
In order to set up the processes, you will need to edit the vessel of your choice, and then go to the Processes tab. This can either be done from the Input...
Helicopter logic in the Shoresim is different for pick up and drop off of personnel. Below you can find diagrams and step-by-step explanations of the two ...
Create working hours and date restrictions to define the time during which vessels cannot operate. Create time restrictions and apply the restrictions to th...
In order to set up the processes, you will need to edit the vessel of your choice, and then go to the Processes tab. This can either be done from the Input...
Daughter craft are small vessels that remain with the SOV during on-site activities and ferry personnel from the SOV to the site for maintenance. Unlike a C...
On floating wind farm installation projects, support vessels work alongside a large installation vessel to carry out the station-keeping and hookup of a flo...