Major component replacements (MCRs) form a critical part of many O&M projects. As a specialized type of maintenance work, they require additional steps to configure within Shoreline.
MCRs are modelled as follows:
- Add a corrective maintenance task on an asset.
- Set the task to use an HLV or a tug, depending on whether you're modeling a fixed-bottom or a floating MCR.
- If you use a tug, you will need to add an onshore crane to your case to conduct the maintenance work.
- If your are using an HLV, you need to add a dedicated CTV to transport crew to the site. Check the Dedicated tasks option when you add the CTV to your case.
- If you're modeling a fixed-bottom MCR, add any lead times you require.
Model a fixed-bottom MCR
To follow these instructions, you will need a case configured with a base, a WTG asset, an HLV, and a dedicated CTV.
- Click on the Build tab.
- Click on the Assets tab.
- Click on your WTG asset.
- Click on the Corrective Maintenance tab.
- Click + Add corrective maintenance.
- Complete the inputs for the MCR.
- Severity should always be set to
Critical
for an MCR. - For Vessel, check
Heavy Lift Vessel
. - Complete the HLV-specific inputs.
- Severity should always be set to
- Click Save.
Add lead times
Lead times determine the length of preparation time required before work on the MCR task can begin or before a logistic can leave base to begin work after receiving a work order.
There are 3 lead times:
- CTV lead time
- Model spot-chartered vessels that require preparation time.
- Available on CTVs, SOVs, helicopters, and daughter craft.
- Set in the logistic’s Activity durations tab.
- Only takes effect when the Spot chartered option is checked on the logistic.
- HLV lead time
- Set at the logistic member level or when first adding the logistic to your case.
- Applies to the HLV when conducting an MCR.
- The process for an MCR:
- Lead time triggered upon task creation.
- Any additional tasks assigned to the HLV during the lead time are bundled together and carried out by the HLV in a single charter period.
- Upon completion of the bundled maintenance tasks, the HLV demobilizes and the charter period ends.
- A new lead time is triggered by the next maintenance task requiring an HLV.
- Task lead time
- Applies at the task level, i.e., regardless of the logistic used.
- Applies in addition to any logistic lead times.
- Multiple lead times are considered consecutively.
- The logistic lead time is only triggered once per charter, when the charter period begins.
- The task lead time occurs on each task.
Add CTV lead time
- Open any Shoreline Design case.
- Click on the Build tab.
- Click on the Logistics tab.
- Add a new, or click on an existing, CTV.
- If adding a new logistic:
- Check the Spot chartered option.
- Click Save.
- Check the Spot chartered option.
- If editing an existing logistic:
- Click on the logistic in the Members tab.
- Check Spot chartered.
- Click Save.
- If adding a new logistic:
- Click on the Activity Durations tab.
- Enter a value for the Lead time.
- Click Add (if creating a new logistic) or Save (if editing an existing logistic).
Add HLV lead time
- Open any Shoreline Design case.
- Click on the Build tab.
- Click on the Logistics tab.
- Add a new, or click on an existing, HLV.
- If adding a new HLV:
- Enter a value for the Logistics lead time.
- Click Next.
- Make changes to the inputs you require.
- Click Add.
- Enter a value for the Logistics lead time.
- If editing an existing HLV:
- Click on the logistic in the Members tab.
- Enter a value for the Logistics lead time.
- Click Save.
- Click Save again.
- If adding a new HLV:
Add task lead time
- Open any Shore Design O&M case.
- Click on the Build tab.
- Click on the Assets tab.
- Click on the relevant WTG asset or add a new one.
- Click on the Corrective Maintenance tab.
- Create or click on a maintenance task.
- Enter a value for the Task lead time.
- Click Save.