This article contains information about which weather type is used in the different steps/processes when running a simulation.


TABLE OF CONTENTS


ConDesign


Crew transfer vessel


Weather criteriaWeather used
Significant wave height access limitAsset weather file
Visibility access limitAsset weather file


Heavy Lift Vessel


Process/Cycle stepWeather used
MobilisingBase weather file
LoadoutBase weather file 
Transit to wind farmAsset weather file
Jacking upAsset weather file
InstallationAsset weather file
Jacking downAsset weather file
Transit to next assetAsset weather file
Transit from wind farmAsset weather file
Arrival at baseBase weather file 


Service Operation Vessel


Weather criteriaWeather used
Significant wave height access limitAsset weather file
Visibility access limitAsset weather file
Wind speed access limitAsset weather file


Helicopter


Weather criteriaWeather used
Wind speed access limitAsset weather file
Visibility access limitAsset weather file
Significant wave height access limitAsset weather file


Cable installation vessel


Process/Cycle stepWeather used
MobilisingBase weather file
LoadoutBase weather file
Transit to wind farmAsset weather file
Cable layingAsset weather file
Cable burialAsset weather file
Transit to next assetAsset weather file
Transit from wind farmAsset weather file
Arrival at baseBase weather file


Towing vessel


Process/Cycle stepWeather used
MobilisingBase weather file
LoadoutBase weather file
Towing to wind farmAsset weather file
Wind turbine hook upAsset weather file
Transit from wind farmAsset weather file
Arrival at baseBase weather file


Crane


Process/Cycle stepWeather used
MobilisingBase weather file
Transit to turbineAsset weather file
Pre-assemblyAsset weather file
Transit from turbineAsset weather file
Arrival at baseBase weather file


Anchor handling vessel


Process/Cycle stepWeather used
MobilisingBase weather file
LoadoutBase weather file
Moving to wind farmAsset weather file
InstallationAsset weather file
Cable layingAsset weather file
Cable burialAsset weather file
Transit from wind farmAsset weather file
Arrival at baseBase weather file


Heavy transport vessel / Feeder / Barge


Process/Cycle stepWeather used
MobilisingBase weather file
LoadoutBase weather file
Transit to wind farmAsset weather file
Jacking upAsset weather file
InstallationAsset weather file
Jacking downAsset weather file
Transit to next assetAsset weather file
Transit from wind farmAsset weather file
Arrival at baseBase weather file


Component transfer vessel


Process/Cycle stepWeather used
MobilisingLoadout Base weather file
LoadoutLoadout Base weather file
Transit to loadoff baseAsset weather file
LoadoffAsset weather file
Transit back to loadout baseAsset weather file
Arrival at loadout baseLoadout base weather file





O&M Design


Crew transfer vessel


Weather criteriaWeather used
Significant wave height access limitAsset weather file
Lowest tideBase weather file


Heavy Lift Vessel


Weather criteriaWeather used
Significant wave height jacking limitAsset weather file
Wind speed crane operation limitAsset weather file
Wind speed limitation reference heightAsset weather file
Lowest tideAsset weather file
MobilisingBase weather file
DemobilisingBase weather file
LoadoutBase weather file


Service Operation Vessel


Weather criteriaWeather used
Significant wave height access limitAsset weather file
Wind speed access limitAsset weather file
Wind speed limitation reference heightAsset weather file
Lowest tideAsset weather file


Helicopter


Weather criteriaWeather used
Wind speed access limitAsset weather file
Wind speed limitation reference heightAsset weather file
Visibility access limitAsset weather file
Significant wave height access limitAsset weather file


Towing vessel


Process/Cycle stepWeather used
Mobilising towing inBase weather file
Transit to assetAsset weather file
DisconnectAsset weather file
Tow to portAsset weather file
Tow to wind farmAsset weather file
Preparation for work at portBase weather file
Demobilisation towing inBase weather file
Mobilisation towing outBase weather file
Preparation for work towing outAsset weather file
HookupAsset weather file
Transit to next assetAsset weather file
Transit to portBase weather file
Demobilisation towing outBase weather file


Crane


Weather criteriaWeather used
Wind speed limit crane operationBase weather file
Wind speed limitation reference heightBase weather file