To approve a resource request, logon as the approver (resource manager in this example) and navigate to the resources tool. Also, notice the pop-up notification and the notifications feature.

Click on the notification icon, then click 'Open'.

Here the resource manager would check the request details by clicking on 'Manage', and then the view (eye) icon and decide to either reassign the request, create plan or reject it.


Once you're satisfied with the request details, click 'Create plan'

The status of the resource request changes from 'Request pending' to 'Plan in progress'. A schedule calendar is now displayed where you are able to assign manpower and logistic to it. Learn more about to How to check a resource request.


As soon as the resource request is approved, a notification will be sent to the original requestor to inform about the approval. It is now possible for both requestor and approver to view, edit or delete the request.