NOTE: The output described in this article is for the first simulation run only.

In the jackup log are mostly the same information available as in the logistic log, but only for the used heavy lift vessels and CTVs for major component replacements. Only the technician groups are not shown.  

An example file is found on the bottom.

CellDescription
Column ADisplays the turbine ID.
Column BDisplays the work order ID.
Column CDisplays the task name, together with the activity.
Column DDisplays the severity of the task.
Column EDisplays the vessel name which does the drop-off of the team for the task.
Column FDisplays the vessel name which does the pick-up of the team for the task.
Column GDisplays the time in the simulation when the task name was created.
Column HDisplays the time the team was dropped off.
Column IDisplays the time the team started working on the task.
Column JDisplays the time the team stopped working on the task.
Column KDisplays the time when the team was picked up.
Column LDisplays the remaining hours required on the task when the task is started being worked on.
Column MDisplays the remaining hours required on the task when the team is finished working for the day.
Column NDisplays the average wind for both drop-off and pick-up.
Column ODisplays the weather year used for the task.
Column PDisplays the total sub-contractor hours used on the task
Column QDisplays the charter cumulative hours.
Row 1Displays the column header information.