The output shows the availability and the loss categories per root cause, and one total category that sums the previous ones. 

The availability summary contains all relevant measurements of production, downtime and availability for the whole simulation experiment. The availability categories are explained below, the rest of the categories are described in the following article, see here.

CategoryDescription
Possible/Potential powerThe amount of energy an asset can produce if it was always operational (never fails or shuts down). Found by calculating energy production using the power curve of the asset and the wind speed at hub height.
Possible uptimeThe number of potential operational hours or the number of hours simulated multiplied by the number of assets
Downtime accumulatedThe sum of downtime for all assets
TBAThe time-based availability for the whole simulation
Possible/potential productionSame as possible power. The maximum possible production if all assets were operational 100% of the time
Actual productionThe production measured for the whole simulation for all assets when operational

Arrival at baseThe time the vessel arrived at base

The report shows aggregate statistics for the whole simulation run in P10-P90, confidence interval, and standard deviation.

When downloading the file it will show the user ID, case ID, title file, and date of simulation. An example file is found on the bottom.

Explanation of the outputs:

CellDescription
Column ADisplays the wind farm name (if set to 'default', this means that there is no wind farm name set on the case).
Column BDisplays the name of the data, which is to be used in accordance with the data in the same row.
Column CDisplays the average value for the referenced row.
Column DDisplays the P10-values for the referenced row.
Column EDisplays the P20-values for the referenced row.
Column FDisplays the P30-values for the referenced row.
Column GDisplays the P40-values for the referenced row.
Column H
Displays the P50-values for the referenced row.
Column IDisplays the P60-values for the referenced row.
Column J
Displays the P70-values for the referenced row.
Column K
Displays the P80-values for the referenced row.
Column L
Displays the P90-values for the referenced row.
Column M
Displays the minimum value for the referenced row.
Column NDisplays the maximum value for the referenced row.
Column O
Displays the standard deviation (read more about standard deviation here).
Column P
Displays the minimum confidence interval (read more about confidence interval here).
Column Q
Displays the maximum confidence interval (read more about confidence interval here).
Row 2Displays the possible power in MWh *with the related P-values, max- and min-values, standard deviation, and the max- and min confidence interval.

*all rows below row 2 uses the same description with the P-values, deviation and confidence interval
Row 3Displays the possible up time in MWh with related values (see row 2).
Row 4Displays the accumulated downtime in MWh. 
Row 5Displays the Time Based Availability in MWh.
Row 6Displays the possible production in MWh.
Row 7Displays the actual production in MWh.
Row 8Displays the lost production in MWh.
Row 9Displays the lost production (root causes) in MWh.
Row 10Displays the total PBA in percent decimal (1=100%).
Row 11Displays the PBA schedule service work WTG in percent decimal (1=100%).
Row 12Displays the PBA Major lead time in percent decimal (1=100%).

Accumulated data for rows 13 to 15.
Row 13Displays the PBA Major lead time - waiting to be scheduled for support vessel in percent decimal (1=100%).
Row 14Displays the PBA Major lead time - waiting to be scheduled for HLV in percent decimal (1=100%).
Row 15Displays the PBA Major lead time - no available support vessel  in percent decimal (1=100%).
Row 16Displays the PBA Major weather delay  in percent decimal (1=100%).
Row 17Displays the PBA Major work WTG in percent decimal (1=100%).
Row 18Displays the PBA Minor work WTG in percent decimal (1=100%).
Row 19Displays the PBA Minor weather delay in percent decimal (1=100%).
Row 20Displays the PBA Minor response time in percent decimal (1=100%)

Accumulated data for rows 21 to 27.
Row 21Displays the PBA Minor response time - No technicians on shift in percent decimal (1=100%).
Row 22Displays the PBA Minor response time - No available technicians on shift in percent decimal (1=100%).
Row 23Displays the PBA Minor response time - No helicopter daylight in percent decimal (1=100%).
Row 24Displays the PBA Minor response time - Emergency response limit in percent decimal (1=100%).
Row 25Displays the PBA Minor response time - No available vessel on shift in percent decimal (1=100%).
Row 26Displays the PBA Minor response time - No available seats in percent decimal (1=100%).
Row 27Displays the PBA Minor response time - Waiting to be scheduled in percent decimal (1=100%).
Row 28Displays the PBA PBA Floating work WTG in percent decimal (1=100%).

Data is for all scheduled or corrective maintenance tasks assigned to a towing vessel - this repeats for rows 29 to 31.
Row 29Displays the PBA Floating weather delay in percent decimal (1=100%).
Row 30Displays the PBA Floating response time in percent decimal (1=100%).
Row 31Displays the PBA Floating towing time in percent decimal (1=100%).
Row 32Displays the PBA External schedule service work in percent decimal (1=100%).
Row 33Displays the PBA External Minor work WTG in percent decimal (1=100%).
Row 34
Displays the PBA External Minor weather delay in percent decimal (1=100%).
Row 35Displays the PBA External Minor response time in percent decimal (1=100%).

Accumulated data for rows 36 to 42.
Row 36Displays the PBA External Minor response time - No technicians on shift in percent decimal (1=100%).
Row 37Displays the PBA External Minor response time - No available technicians on shift in percent decimal (1=100%).
Row 38Displays the PBA External Minor response time - No helicopter daylight in percent decimal (1=100%).
Row 39Displays the PBA External Minor response time - Emergency response limit in percent decimal (1=100%).
Row 40Displays the PBA External Minor response time - No available vessel on shift in percent decimal (1=100%).
Row 41Displays the PBA External Minor response time - No available seats in percent decimal (1=100%).
Row 42Displays the PBA External Minor response time - Waiting to be scheduled in percent decimal (1=100%).
Row 43Displays the PBA Root causes total in percent decimal (1=100%).

Accumulated data for rows 11-42